Local Plan Timetable (Published 30 June 2026)
| Local Plan Stage | Date |
|---|---|
Publish ‘Notice of intention to commence Local Plan preparation’Publication of the notice gives communities and stakeholders advanced notice of plan-making and sets out how and when they can get involved. The notice must be published at least 4-months before Gateway 1. |
30 June 2026 |
Start of first formal consultation (notice of scoping consultation)This consultation will invite feedback from stakeholders on how to engage with them during preparation of the local plan and what the plan should contain. |
7 September 2026 (21 days) |
Date when representations to the scoping consultation must be receivedAll comments (representations) on the scoping consultation must be received by this date. |
23:59pm on 28 September 2026 |
Gateway 1 (publication of self-assessment summary)This new requirement is a self‑assessment summary confirming that we have published the timetable and notice, completed the scoping consultation, and have a project plan in place to begin the formal stage of preparing the local plan. Once we complete Gateway 1, we have 30 months to prepare and adopt the plan. |
30 October 2026 |
Start of second formal consultation (proposed Local Plan content and evidence consultation)This consultation will focus on the content of the local plan and the evidence that has been commissioned to support the plan. It will set out the proposed vision, aims and objectives, and a summary of the policy topics the plan will cover. |
19 March 2027 (6 weeks) |
Date when representations to the proposed Local Plan content and evidence consultation must be receivedAll comments (representations) on the proposed Local Plan content and evidence consultation must be received on or before this date. |
30 April 2027 |
Gateway 2This requirement is a formal method of obtaining feedback from a planning inspector on the draft plan and supporting evidence, ensuring our approach aligns with national policy, guidance and legislation. |
4 January 2028 |
Start of third formal consultation (proposed Local Plan consultation)This 8 week consultation is on the final version of the plan and includes all policies and the proposed site allocations. |
4 February 2028 (8 weeks) |
|
Date when representations on the proposed Local Plan consultation must be received All comments (representations) on the proposed Local Plan content and evidence consultation must be received on or before this date. |
31 March 2028 |
Gateway 3 (prescribed requirements assessment)This requirement is a final check by an external assessor (planning inspector) to confirm that the plan meets planning regulations and the tests of soundness, before formally submitting it for Examination. |
7 July 2028 |
Submission of the proposed Local Plan to the Secretary of State for independent ExaminationThe proposed Local Plan must be submitted for an independent Examination carried out by a Planning Inspector. The Examination should last no longer than 6 months. |
30 October 2028 |
Adoption of the proposed Local PlanConsideration of adoption of the Local Plan by the new Mid Hampshire Authority as the statutory development plan covering the former Winchester District. |