St. Maurice's Covert

St. Maurice's Covert

Improvements to St. Maurice's Covert
StMCovert

 

ScottWhitbyStudio have developed further the public realm improvement scheme for St. Maurice’ s Covert. The proposal was initially developed through close conversations with the residents and users of St. Maurice’ s Covert, as well as observations of the space through CCTV footage and filming. 

The proposed scheme includes a thorough clean of the space, installing new lighting for the thoroughfare and to highlight the historic tower, and some repaving.

 

 

A great deal of care has been given in how we design to make St. Maurice’ s Covert, a forgotten public space in the centre of Winchester, a new civic space for all its users, and a key gateway point to the Cathedral Grounds- we are hoping these new elements will bring life and activity to the space and become a space where people will want to be and look after.

St. Maurice's Covert details

Cabinet Member

Councillor Kelsie Learney

Start Date

01/06/2017

Expected End Date

30/07/2021

Key Steps/Milestones

  • Civil works completed by Rocon in May 2020 which included the resurfacing work adjacent to Market Lane, and installation of new street furniture.
  • Works on the installation of the structural framework and the memorial stones to start in March 2021 and should take approx. 6 weeks.  
  • A interpretation panel will also be installed detailing information about the memorial stones.
  • The ceiling and lighting works will follow this - date to be confirmed.

Latest Status

  • The civil works have now been completed by Rocon. These works consisted of resurfacing with natural stone the area adjacent to Market Lane, new street furniture, water fountain and new bike stands.
  • Gravestones successfully removed from site.
  • Repairs and dressing gravestones underway with stone conservator and wall mounting details for the Tower being finalised with a structural engineer.
  • Works have started on installing the structural framework on the tower wall through the tower walkway, with the installation of the memorial stones, from March 2021 and will be completed in approx. 6 weeks.
  • Interpretation panel detailing information about the memorial stones to be installed too.

Consultation

The project has been developed thanks to a steering group formed of councillors, council officers and local businesses, with architects Scott Whitby Studio drawing up ideas and consulting the public on designs for the space.

Next Steps

  • Mounting the framed structure onto the wall of the Tower walkway.
  • Installing the gravestones into the framed structure.
  • Installation of the interpretation panel.
  • Ceiling and lighting works to be undertaken.
  • Looking at various options on how we can illustrate the history of the Covert.
  • Reviewing of CCTV.
  • Improving the display of artefacts in the public conveniences’ window.

Top
Winchester City Council logo

Cookies Policy

As is common practice with many websites this site uses cookies, which are small files that are downloaded to your computer, used to improve your visit to this website.

It is recommended that you leave on all cookies if you want to enjoy this website.

Review your privacy settings