The City Council intends to make improvements to the site in the short-term and to propose changes that will improve the flow of buses through the town and increase pedestrian safety. In the longer-term, the purchase will bring new opportunities and have significant benefits for the regeneration of central Winchester and the continuing provision of bus services. 

Project Summary

Project Name Bus Station
Portfolio Holder Cllr Miller and Cllr Warwick
Start Date 10/07/2017
Key Steps/Milestones
  • Appoint contractor – late June
  • Planning approval for demolition – early July
  • Implement temporary measures for buses and taxis during construction – early July
  • Bus station closes and works commence – mid July
  • Works begin on St Georges Street and Middle Brook Street – late August
  • Bus station re-opens and buses are re-routed along Tanner Street – early Sept 

Latest Status

The City Council purchased the bus station in April 2017. Interim works are currently underway over the Summer months. 