Barton Farm

The Barton Farm Major Development Area is located to the north of Winchester and will provide 2,000 new homes including much needed affordable housing, along with community facilities, a new school and a new park and ride facility to serve the north of Winchester.

Cala Homes intend to recommence house building over the summer 2016.

Project Summary

Project Name Barton Farm
Portfolio Holder Cllr Weston
Start Date 01/06/2016
Expected End Date 01/12/2026
Key Steps/Milestones

  • Construction of Second access onto Andover Road. Summer 2017
  • Submission of Phase 2 Reserved matters application 2017 date to be agreed
  • Construction of Primary School. Date to be agreed with HCC/ Cala Homes

Latest Status

First houses are being constructed with first occupations expected in Spring 2017 . Highway access onto Andover Road now fully open and operational


Community Facilities to be built as part of Phase 2 currently being considered following a stakeholder Workshop in September

Last Committee Report

(see link)

Next Steps

Barton Farm Forum Meeting – 14 December 2016