Barton Farm/Kings Barton

The Barton Farm Major Development Area is located to the north of Winchester and will provide 2,000 new homes including much needed affordable housing, along with community facilities, a new school and a new park and ride facility to serve the north of Winchester.

Cala Homes intend to recommence house building over the summer 2016.

Project Summary

Project Name Barton Farm/Kings Barton
Portfolio Holder Cllr Vicki Weston
Start Date 01/06/2016
Expected End Date 01/12/2026
Key Steps/Milestones

Current status - On Schedule

  • Construction began at the site (Phase 1B) in Summer 2016
  • First occupations are scheduled for on or about 31 March 2017
  • Phase 1A scheduled to commence in May/June 2017
  • Construction of new school to commence in June/July 2017
  • New southern junction into site (Andover Road) to be constructed Summer 2017
  • Phase 2 proposals to be finalised Autumn 2017
  • Phases 2-5 to be designed and constructed between now and 2026
Latest Status
  • Construction progresses.  20 homes have been sold.  First occupations took place on 31 March.  Further occupations will occur as and when homes are complete.
  • Barton Meadows fencing work is completed.  The site will be 'launched' in May 2017.
  • Planning Conditions for 1A have been discharged.

Consultation

Consultation will continue through the forthcoming planning application process.  Public participation is also encouraged at the Barton Farm Forum.

Last Committee Report

(see link)

Next Steps

The next Barton Farm Forum Meeting is on Wednesday 12 July 2017 at 6.30 pm