Privacy settings

Leisure Centre update

Detailed analysis of a wide range of options for a new leisure centre in Winchester has been completed.

An all-party working group of Winchester City Council members commissioned an extensive feasibility study to reassess options for providing new leisure facilities at either North Walls or Bar End.

This was in response to feedback from a public exhibition in November 2013 and calls to examine a wider range of options for a replacement leisure centre in more detail.
Cllr Robert Humby, the Leader of Winchester City Council, said:

Roberts Limbrick Architects, in conjunction with other specialist consultants, were commissioned to provide advice after a competitive tender.

Roberts Limbrick’s expertise is recognised nationally, as they have been a leading contributor to the design of public and commercial leisure facilities for over 25 years. They have experience working on many public sports facilities and act as expert advisors to Sport England.

Their report illustrates five options, presenting three site configurations for North Walls and two for Bar End. All the options retain the flexibility to incorporate either a 25m pool with a learner pool or a 50m pool within the centre.


The options considered are:

North Walls Option 1 Existing leisure centre footprint - built in two phases
  Option 1A Existing leisure centre footprint - built in one phase
  Option 2 Existing location in two phases – including a new indoor bowls centre within the leisure centre
  Option 2A  Existing location built in one phase – including a new indoor bowls centre within the leisure centre
  Options 3 Tennis courts and ATP site
 Bar End Option 4 WCC ex-depot site and partially on Tesco-owned Garrison ground
  Option 5 Combination of WCC, HCC and University of Winchester land
 Refurbishment Option 6  Extend the life of existing building


 The report will be considered by the City Council’s Cabinet in December with a recommendation to narrow down the options to allow more detailed cost evaluation to take place. The all-party councillors’ working group has indicated that it would support a recommendation that Options 2, 4 and 5, are taken forward along with the refurbishment option.

Estimated costs range from £22.3m - £27.6m for the options with a 25m pool and from £23.7m - £29m for the options with a 50m pool.

At this stage the estimates do not include costs such as land acquisition.

The Council is evaluating options to determine whether or not a replacement facility is affordable given the significant pressures on its finances. It has not made any commitment to proceed and the final decision will be a matter for the Council as a whole.

The report, Outline Facility Brief and Site Options Appraisal, is available on the Sport and Leisure Feasibility page.

Top
Winchester City Council logo

Cookies Policy

This site uses cookies to store information on your computer.

Some of these cookies are necessary to make the site work. We’d also like to use optional cookies to help improve your experience on the site. You can manage your optional cookie preferences below. Using this tool will set a cookie on your device to remember your preferences. Your preferences can be changed at any time.

Review your privacy settings