The Clean Air Act 1993 introduced a range of regulations to control smoke emissions and the height of chimneys.

Under Section 14 of the Act, the height of a chimney has to be approved by the Local Authority. The Local Authority can attach conditions to the approval. Without an approval, it is an offence to cause or knowingly permit a furnace to be used to:

  • Burn pulverised fuel.
  • Burn at a rate of 45.4kg or more an hour any solid matter, or
  • Burn at a rate equivalent to 366.4kW or more any liquid or gaseous matter.

An application for chimney height approval must contain adequate information to enable the necessary calculations to be carried out. A copy of our application form can be downloaded from the link on this web page.

An application for approval for a chimney must be considered within 28 days of receipt, unless a longer time period had been agreed between the applicant and the Council.

Planning permission will usually be required for a chimney and associated plant.

Control of Dirt and Grit from Furnaces

The Clean Air Act 1993 in addition to chimney height approval requires, subject to certain exemptions, that furnaces with a heating capacity greater that 16.12 kilowatts are to be provided with plant for arresting grit and dust as approved by the authority.

Downloads:
File format File title File size / Download time
Adobe PDF Logo

Chimney Height Approval Application Form

142K
56Kbps Modem: 21 Seconds
Broadband: 1 Second

Click here to download Acrobat PDF Viewer

Contact Us

Customer Service Centre
Winchester City Council
City Offices
Colebrook Street
Winchester
Hampshire
SO23 9LJ

Tel: 01962 840 222

Online enquiry form

This site is valid XHTML.
This site was built with valid CSS.
This site is built to AAA accessibility standards
Browse Aloud enabled
Content Managed Website by weblabs CMS